Quick Glance: 69/13.2 kV

Description:

Toth & Associates provided electrical, civil, and structural engineering design services for Lepanto North Substation located in Lepanto, Arkansas. The project consisted of constructing a new 69/13.2 kV substation on MCEC’s system. The substation is fed by on 69 kV transmission line and provisions were made for a future second line. Initially, only one transformer was installed but will ultimately be a two-transformer station.