Summerville – Hampton 115 kV Transmission Line

Summerville – Hampton 115 kV Transmission Line

Client: Ouachita Electric Cooperative

Location: Camden, Arkansas

Length: 10.7 miles

Voltage: 115 kV

This project consisted of construction of a new 115 kV Transmission Line with distribution underbuild and distribution underground. The line consists of primarily single-pole structures. The line runs between the Summerville substation and Hampton substation.

Design

  • Create Plan and Profile
  • Bill of Materials
  • Specify and Procure Steel Poles
  • Staking
  • Assembly Drawings

Contract

  • Contract Administration for Line Construction
  • Observation of Construction