Ouachita Electric Cooperative – Summerville 115 kV Transmission Design & Environmental Impact Statement
Client: Ouachita Electric Cooperative
Location: Summerville, Arkansas
Length: 13.5 miles
Voltage: 115 kV
Ouachita Electric Cooperative – Summerville 115 kV Transmission Design & Environmental Impact Statement
Description:
Establish route, establish & procure right-of-way (ROW), and design & administer construction contracts for approximately 13.5 miles of 115kV line from new Summerville Switch Station (on AEP’s existing 115kV line) to Ouachita’s existing Summerville distribution station.
Arkansas PSC Filing
- Certificate of Environmental Compatibility and Public Needs (CECPN) Filing with Arkansas Public Service Commission
- Environmental Impact Statement
ROW
- Define Centerline
- Manage Survey
- Easement Negotiation and Procurement
- SWPP
Design
- Create Plan and Profile
- Bill of Materials
- Specify and Procure Steel Poles
- Staking
- Assembly Drawings
Contract
- Contract Administration for ROW Clearing and SWPP Implementation
- Contraction Administration for Line Construction
- Construction Observation for Clearing and Construction